Upgrading of Berawan WTP to Meet Increasing Water Demand in Limbang

Must read

The upgrading of Berawan Water Treatment Plant in Limbang will overcome the increase of clean water supply demands for consumers living in Limbang Town and its surrounding areas.

Once fully commissioned, the plant – which is managed by LAKU Management Sdn Bhd – should have a production capability of up to 40 million litres daily (MLD), an increase from 20 MLD prior to its upgrade.

Layout of Berawan Water Treatment Plant after upgrading works. Courtesy of JBALB

According to the project implementing agency Sarawak Rural Water Supply Department (JBALB), the existing Berawan Water Treatment Plant is located near the junction of Jalan Kubong and Jalan Medamit, which is approximately 10 km from Limbang Town.

A Google Earth map showing the scope of the upgrading project. Courtesy of JBALB

At a cost of around RM33.5 million, the upgrading project began on 4 March 2019 and was supposed to be completed on 3 September 2020, but unforeseen circumstances such as the COVID-19 pandemic led to a delay in the project and was given a revised completion date of 12 January 2021.

The scope of the project involved the construction of:

  1. A new 8.8 km, 500 Ø Ductile Iron Cement Lined (DICL) pipeline from Sungai Pandaruan Raw Water Intake to Berawan Water Treatment Plant
  2. A new 20 MLD Process Plant comprising:

(i)  Four flocculation tanks;

(ii)  Four sedimentation tanks;

(iii)  Six filters; and

(iv)  A control gallery, including capacity upgrading of existing treated water pumping station, chemical facilities, electrical plant and new supervisory control and data acquisition (SCADA) system

SCADA system that was installed as part of the upgrading project. Photo courtesy of JBALB
  1. A new 500 Ø DICL treated water pipeline from Berawan WTP to 6.8 ML reservoir at approximately 1.0 km

JBALB stated that the upgrading project was physically completed, and that the internal full testing and commissioning of the water treatment plant was conducted from 5 to 8 February 2021.

The newly upgraded plant’s official seven-day continuous full-testing and commissioning was scheduled from 15 to 22 March 2021.