- Advertisement -spot_img
4,848
published news
and counting

Spaoh Roads To Be Completed This Year

Must read

The two road projects in Spaoh namely Ulu Paku/ Ulu Gerenjang/ Ulu Krian/ Ulu Kota Road (Phase 1) and the Penom/ Ulu Bayor/ Danau Road (Phase 1) are expected to be completed this year.

This was said by the Divisional Engineer of JKR Betong Division, Chiresly Ak Francis Kureng during a recent interview with RAKAN Sarawak at Betong.

Divisional Engineer of Public Works Department (JKR) of the Division, Chiresly Ak Francis Kureng

At the time of writing, it was noted that the Ulu Paku/ Ulu Gerenjang/ Ulu Krian/ Ulu Kota Road (Phase 1) road project is 42.01 per cent behind schedule, while Penom/ Ulu Bayor/ Danau Road (Phase 1) road project 45.46 behind schedule.

With a stretch of 6.921 kilometres, the Ulu Paku/ Ulu Gerenjang/ Ulu Krian/ Ulu Kota Road is meant to link two major roads in Betong which are Ulu Rimbas and Ulu Paku Road
The first of three bridges at Jalan Ulu Paku/Ulu Gerenjang/Ulu Krian/Ulu Kota which is said to be 16 metres long and to be completed by August 2022

Scope of work for Penom/ Ulu Bayor/ Danau Road (Phase 1) road project;

  • Roadworks – construction of 7.43 kilometres x 4.5 metre width (gravel road)
  • Drainage – 6 nos. of HDPE culverts
  • Bridge works – 1 no. of 36 metre length x 3.7 metre width RSJ bridge, steel decking
  • Initial schedule completion date: 13 October 2021
  • Contract sum: RM9, 994,400.00

(Source: JKR Betong Division)

Scope of work for Ulu Paku/ Ulu Gerenjang/ Ulu Krian/ Ulu Kota Road (Phase 1) road project;

  • Total length of the project is 6.921 kilometre (R1)
  • Total culvert = 10 nos
  • Total bridge = 3 nos
  • Initial schedule completion date: 30 April 2021 
  • Contract sum: RM15, 255, 000.00

(Source: JKR Betong Division)

The reason of delay for the construction of Penom/ Ulu Bayor/ Danau Road (Phase 1) includes land acquisition (which has been resolved), the CMCO period that was affecting mobilization of machineries from Sibu to the site, the weather (rainy season), insufficient machineries and the termination of previous sub-contractors due to poor performance at the early stage.

The second project, Jalan Penom/Ulu Bayor/Danau is also preorted to be 45 per cent behind, at the time of writing
With a stretch of 7.43 metre in length and 4.5 metres in width, the scope of work for Jalan Penom/Ulu Bayor/Danau includes drainage and bridge work of 36 metre in length and 3.7 metre in width

As for Ulu Paku/ Ulu Gerenjang/ Ulu Krian/ Ulu Kota Road (Phase 1), the reason for delays is also due to poor performance of previous contractor.

According to Chiresly, the 6.9-kilometre Ulu Paku/ Ulu Gerenjang/ Ulu Krian/ Ulu Kota Road is meant to link two major roads in Betong which are Ulu Rimbas and Ulu Paku Road.

“We have spoken with the contractors and they have come up with a new construction team and according to them, they have already mobilised the new team to site and if the weather permits, they should be able to complete the project by this year,” he said.

Click to rate this post!
[Total: 0 Average: 0]
- Advertisement -spot_img

More articles

- Advertisement -spot_img

Latest article